Tauranga Harbour Development


Category
Engineering Site (eg Portland cement works, Maori fortifications)

Description
From a shallow coastal port in 1952, the Port of Tauranga has been developed into New Zealand’s largest export port. The new Tauranga Harbour Bridge is an integral part of the total port complex.

The Port of Tauranga, located in the Bay of Plenty on the North Island’s East Coast, is a natural harbour and the only deep water port between Auckland and Wellington providing a safe berthage in all weather.

Here the combined skills of harbour and bridge engineers have converted a once shallow coastal port into New Zealand’s largest export centre.

In 1958 the Tauranga Harbour Board commissioned a study of the harbour by the Wallingford Hydraulics Research Station, England. Results of this physical model study led to a dredging programme to deepen the entrance, from the cutter channel and deepen the Maunganui Roads alongside the Mount Maunganui wharves. Some dredge material was pumped ashore to reclaim both behind the new wharves at Mount Maunganui and some 80 ha of land at Sulphur Point.

In 1983, the Bay of Plenty Harbour Board commission a mathematical computer model of the harbour. This was undertaken by a term of scientists from the Ministry of Works and Development, the Danish Hydraulics Institute, Waikato University and Dr K Black. The model was established on the Waikato University computer using historical records and freshly collected data. It has been used to study the effects of projects such as the Harbour Bridge, Sulphur Point wharf development and further dredging, on the tidal flows and sediment transfer in the harbour and entrance.

In 1984, a Ship Manoeuvring Simulation study was conducted at the Maritime Research Institute in the Netherlands (MARIN) to help determine the capability of the port to handle safely larger or different types of ships. The study used port pilots on a computer simulator under a variety of conditions such as wind, tide, tug power and channel widths.

Meanwhile to keep pace with progress and demand, an almost continuous berth-building programme was undertaken, accompanied by channel and harbour deepening, reclamation works, construction of port facilities, and the acquisition of floating and shore plant. In particular:

+ Between 1961 and 1978 port draught was increased from 7.31m to 10.7m to handle the 68% increase in shipping (269% increase in net register tonnage)
+ The main wharf was lengthened from the original 372m to 1843m (Since lengthened to 2055m)
+ Large transit storage sheds were built
+ A 600 tonne slipway and jetty were constructed.
+ A linkspan and a $2 million Forest Industry Terminal was established to serve the direct roll-on/roll-off service to Australian and South Pacific island ports.
+ A heavy lift multi-purpose gantry crane was installed at a cost of $3.9 million, and became operational in September 1979.
+ A bulk Cement/Tanker berth was constructed and became operational in June 1980
+ The original berths were progressively deepened.

A continuous concrete quay-type wharf structure currently 2005 m long now provides a nominal 11 berths plus a separate specialised 80m concrete dolphin type berth for tankers, cement and woodchips located to the south of the main quay. These modern concrete structures include some of the strongest wharf structures in New Zealand.

The new Tauranga Harbour Bridge is an integral part of the total port complex.

This 480m bridge, over the Stella Passage, joining the two sides of the harbour development, was constructed ashore and then cantilevered into place. It was completed, at a cost of about $25 million, two months ahead of schedule and was opened in March 1988. It is estimated that toll charges will clear all debt by 1997 or 1998.

Designers: Ministry of Works 1953-1968
Tauranga Harbour Board 1968-1970
Bay of Plenty Harbour Board 1970-1988
Port of Tauranga Ltd 1988-1990
Major constructors: Ministry of Works; Bay of Plenty Harbour Board.

Harbour Bridge
Design: Murray-North Ltd
Construction: Fletcher Construction Co Ltd
Project Manager: Beca Carter Hollings & Ferner Ltd


Heritage recognition
IPENZ “Engineering to 1990” project
This item of New Zealand’s engineering heritage was recognised as part of the IPENZ “Engineering to 1990” project which the Institution organised to help celebrate the country’s sesquicentenary in 1990. A plaque was unveiled to mark the significance of this harbour development as part of the development of the nation.


Attachments

No Attachments

Location
Tauranga (Sulphur Point) and Mount Maunganui



Region/s
Bay of Plenty